Skip Navigation

2023 Asphalt Resurfacing Program

North Bay, ON – April 17, 2023 – The City of North Bay plans to repave 23 sections of roadway this year as part of its annual asphalt resurfacing program.

A request for tender, which was recently issued for the $3.6 million program; closes on May 4. Once a contract has been awarded, work will continue throughout the summer and fall.

The list of roads for rehabilitation as part of the program is developed through a quantitative and objective process, which was updated by a third party for the City in 2021. 

Roads are scored and ranked based on traffic usage and other criteria including riding comfort, noise, cracking and stress.

Though the City has traditionally prioritized arterial and collector roads, it has started in recent years to tackle lower-usage residential and rural roads that are considered to be in the poorest condition.

Depending on condition, roads included in the program will undergo various types of treatments, including milling and paving, pulverizing and paving, overlay and reconstruction. Roads requiring major reconstruction, however, are typically addressed as standalone projects and also include other infrastructure improvements.

The annual re-surfacing program also includes ongoing crack sealing, which helps extend the life of roadways. This is in addition to patching and work on rural roads which also takes place annually.  

The following list may be subject to change based on the tender bids and costing received.

 

GOLF CLUB RD

55m North AIRPORT RD - OBRIEN

Pulverize and Pave

BOOTH RD

30m SOUTH OF BUNTING TO ~130m

Pulverize and Pave

JANICE

SKI CLUB - MCKEOWN

Pulverize and Pave

LAMORIE

BRIDGE - LEGION ENTRANCE

Pulverize and Pave

MATTAWA

HARRIET - MAIN

Pulverize and Pave

TACKABERRY

BIRCHWOOD - PARKWOOD

Pulverize and Pave

MULLIGAN

TALON - BEAVER ~200m

Pulverize and Pave

PRINCESS

FRASER - FERGUSON

Pulverize and Pave

STRATHCONA

VAN HORNE - MACDONALD

Pulverize and Pave

THIRD

FERGUSON - FRASER

Pulverize and Pave

PEARCE ST

GREENHILL - DAZIEL

Mill and Pave

RANCIER ST

DELLANDREA DR - BOLTON

Mill and Pave

WYLD ST

OAK ST E - McINTYRE ST E

Mill and Pave

FODOR

LAKESHORE - WHITNEY

Mill and Pave

BLOEM

ALGONQUIN - BROWNING

Mill and Pave

SCOLLARD

BROWNING - BEATTIE

Overlay

DANE

FROST - HARRISON

Overlay

LAKE HEIGHTS

SAGE - MELINA CLOSE

Overlay

MCINTYRE

HARVEY - DURRIL

Full Asphalt Depth Removal and Pave

HIGH ST

CHIPPEWA ST W - OLIVE

Full Asphalt Depth Removal and Pave

CARMICHAEL

300m SOUH OF AIRPORT RD. – VOODOO CR.

Partial Reconstruction (Gran ‘A’ and Asphalt)

BURNS PART 1

GREENWOOD - ELMWOOD

Full Reconstruction (Gran ‘A’ & ‘B’ and Asphalt)

BURNS PART 2

MAPLEWOOD - TACKABERRY

Full Reconstruction (Gran ‘A’ & ‘B’ and Asphalt)

2023 Asphalt Resurfacing Program
Notifications
or
Contact
Gord Young
Communications Officer
gord.young@northbay.ca (705) 474-0626 x.2505